4.3 Water Quality and Hydrology
4.3 Water Quality and Hydrology
*Introduction
*Impacts Evaluated in Other Sections
*Affected Environment (Setting)
*Wastewater Quality
*Groundwater Quality
*Water Quality Regulations
*Goals, Objectives, and Policies
*Evaluation Criteria with Points of Significance
*Methodology
*Environmental Consequences (Impacts) & Recommended Mitigation
*Cumulative Impacts
*
List of Tables
Table 4.3-1 White Slough Water Pollution Control Facility Effluent Quality
*Table 4.3-2 White Slough Water Pollution Control Facility Groundwater Monitoring
*Table 4.3-3 General Plan Goals, Objectives, and Policies – Water Quality and Hydrology
*Table 4.3-4 Evaluation Criteria with Point of Significance – Water Quality and Hydrology
*Table 4.3-5 Water Quality and Hydrology Impacts
*Table 4.3-6 10-year Storm Project Site Conditions
*Table 4.3-7 Allowable Discharge based on Existing Site Conditions
*4.3 Water Quality and Hydrology
This section discusses project impacts on water quality and hydrology that will result from each project alternative.
Impacts Evaluated in Other Sections
Some issues that may affect surface water quality and hydrology have been evaluated in other sections. Potential water quality and hydrology impacts addressed in other sections are:
Water Quality Related to Human Health. These issues are addressed in Section 4.4 Public Health and Safety.
Erosion Due to Construction. Erosion caused by construction within designated construction zones is addressed in Section 4.2 Geology, Soils, and Seismicity.
Affected Environment (Setting)
The project will use treated wastewater from the White Slough Water Pollution Control Facility (treatment plant) for irrigation and fire control purposes and possibly as supply for restroom toilets. Treatment plant improvements will occur as part of the project so that the recycled water will comply with Title 22 criteria for reclamation. Water quality also will be monitored as required by Title 22. With the treatment plant improvements, total suspended solids (TSS) will be reduced to 10 mg/L (pers. comm Rob Beggs, West-Yost Associates). Available effluent quality data are summarized in Table 4.3-1.
Because of treatment plant upgrades from secondary to tertiary treatment, there is a reduction in pollutant loads of some constituents, such as bacteria and TSS, relative to existing conditions. Thus, the impact to groundwater quality is reduced relative to existing conditions. The project will also use groundwater wells for potable water for the facility. The impact of groundwater quality on human health is discussed in section 4.4 Public Health and Safety. Water quality from samples collected from two monitoring wells on the project grounds as part of the treatment plant monitoring wells quarterly analysis are presented in Table 4.3-2.
|
White Slough Water Pollution Control Facility Effluent Quality |
||||||
|
1995 |
1996 |
1997 |
1998 |
1995-1998 Average |
Median and Maximum (in parentheses) a,b |
|
|
NH3-N (mg/L) |
1.4 |
2.4 |
1.6 |
0.8 |
1.5 |
N/A |
|
NO2-N (mg/L) |
0.40 |
0.85 |
0.35 |
0.45 |
0.51 |
N/A |
|
NO3-N (mg/L) |
8.0 |
7.5 |
7.1 |
6.2 |
7.2 |
N/A |
|
TSS (mg/L) |
10.8 |
8.3 |
11.2 |
11.2 |
10.4 |
(10)c |
|
Settleable Solids (mg/L) |
0.29 |
0.0016 |
0.0044 |
0.013 |
0.077 |
N/A |
|
pH |
7.2 |
7.0 |
7.0 |
7.0 |
7.1 |
N/A |
|
°F |
73 |
74 |
74 |
73 |
73 |
N/A |
|
BOD (mg/L) |
9.0 |
8.3 |
9.0 |
8.6 |
8.7 |
(10)c |
|
COD (mg/L) |
39 |
25 |
26 |
27 |
29 |
N/A |
|
Total Coliform Bacteria |
N/A |
N/A |
N/A |
N/A |
N/A |
2.2 (23)c |
|
Total Dissolved Solids (mg/L) |
N/A |
N/A |
N/A |
N/A |
N/A |
410 |
|
Cyanide(µg/L) |
N/A |
N/A |
N/A |
N/A |
N/A |
<10 (49) |
|
Lindane (µg/L)d |
N/A |
N/A |
N/A |
N/A |
N/A |
0.01 (0.051) |
|
Total Lead (µg/L) |
N/A |
N/A |
N/A |
N/A |
N/A |
1.5 (10) |
|
Total Mercury (µg/L) |
N/A |
N/A |
N/A |
N/A |
N/A |
<0.2 (0.63) |
|
Total Zinc (µg/L) |
N/A |
N/A |
N/A |
N/A |
N/A |
110 (160) |
|
Source: White Slough Water Pollution Control Facility, 2000 |
||||||
|
||||||
|
White Slough Water Pollution Control Facility Groundwater Monitoring |
||||||
|
Well WSM# |
Date |
Nitrates (mg-N/L) |
Specific Conductivity (µmhos/cm) |
Fecal Coliform (mpn/100mL) |
COD (mg/L) |
Water Level (feet above mean sea level) |
|
6 |
3/16/99 |
21 |
1320 |
<2 |
12 |
-1.75 |
|
7 |
3/16/99 |
16 |
1250 |
<2 |
21 |
-0.68 |
|
6 |
5/12/99 |
25 |
1390 |
<2 |
NDa |
-2.58 |
|
7 |
5/12/99 |
16 |
1110 |
<2 |
12 |
-0.6 |
|
6 |
9/3/99 |
55 |
1600 |
<2 |
8.2 |
-5.33 |
|
7 |
9/3/99 |
11 |
1300 |
<2 |
8.2 |
-4.27 |
|
6 |
11/3/99 |
15 |
1390 |
<2 |
8.2 |
-5.17 |
|
7 |
11/4/99 |
15 |
1250 |
<2 |
8.2 |
-2.77 |
|
6 |
1999 average |
29 |
1425 |
<2 |
9.5 |
-3.71 |
|
7 |
1999 average |
14.5 |
1228 |
<2 |
12.4 |
-2.55 |
|
||||||
Surface water quality is regulated to protect aquatic life and human health according to the provisions of the Federal Clean Water Act (and associated federal regulations) and the California Porter-Cologne Water Quality Control Act, referred to respectively as the Federal and State Acts. The State Act established the nine Regional Water Quality Control Boards (Regional Boards) and the State Water Resources Control Board (State Board). In California, the discharge permitting provisions of the Federal Act have been delegated by U.S. EPA to the State and Regional Boards. The Federal Act has led to the development of aquatic life water quality criteria (enforceable) and water quality guidelines (non-enforceable); the State Act has led to water quality objectives (enforceable) to protect aquatic life from adverse impacts for numerous water quality constituents. The criteria, guidelines, and objectives are hereinafter referred to collectively as criteria.
Requirements for wastewater reuse are established in Title 22 Chapter 3. Section 60313b Landscape Irrigation states that reclaimed water used for the irrigation of parks, playgrounds schoolyards, and other areas where the public has similar access or exposure shall be at all times an adequately disinfected, oxidized, coagulated, clarified, filtered wastewater or a wastewater treated by a sequence of unit process that will assure an equivalent degree of treatment and reliability. The wastewater shall be considered adequately disinfected if the median number of coliform organisms in the effluent does not exceed 2.2 per 100 ml, as determined from the bacteriological results of the last 7 days for which analyses have been completed, and the number of coliform organisms does not exceed 23 per 100 ml, in any sample.
The existing Waste Discharge Requirements for White Slough Water Pollution Control Plant (Discharge Permit) provides reclamation specifications, receiving water limitations, and groundwater limitations designed to protect groundwater and surface waters and to protect public health and safety, including the following:
|
Constituent |
Units |
Monthly Average |
Daily Maximum |
|
BOD5* |
mg/l |
40 |
80 |
|
Settleable Matter |
ml/l |
0.2 |
0.5 |
* 5-Day, 20şC, Biochemical Oxygen Demand
a. Tail water must be returned and all applied reclaimed water and any additional supplement irrigation water must infiltrate completely within a 48-hour period.
b. Ditches not serving as wildlife habitat should be maintained free of emergent, marginal, and floating vegetation.
c. Low pressure and unpressurized pipelines and ditches accessible to mosquitoes shall not be used to store reclaimed water.
Numeric and narrative water quality criteria have been developed by EPA and other agencies to protect aquatic life and to protect against aesthetic water quality impacts.
Specific regulations that relate to inland surface waters are described below.
The inland surface waters in the project area are within the jurisdiction of the Central Valley Regional Water Quality Control Boards (CVRWQCB). The CVRWQCB has a Water Quality Control Plan for basins within its jurisdiction (Basin Plan). The Basin Plan identifies beneficial uses of waters, establish numeric and narrative objectives for protection of beneficial uses, and set forth policies to guide the implementation of programs to attain the objectives.
The State Water Resources Control Board (SWRCB) Water Quality Control Plan for the San Francisco Bay/Sacramento-San Joaquin Delta Estuary (Bay-Delta Plan) establishes water quality objectives which, when implemented will: (1) provide reasonable protection of municipal, industrial, and agricultural beneficial uses; (2) provide reasonable protection of fish and wildlife beneficial uses at a level which stabilizes or enhances the conditions of aquatic resources; and (3) prevent nuisance for the San Francisco Bay/Sacramento-San Joaquin Delta Estuary.
The Federal Rule, Establishment of Numeric Criteria for Priority Toxic Pollutants for the State of California (California Toxics Rule or CTR, promulgated May 18, 2000), provides for the State of California numeric water quality criteria for priority toxic pollutants necessary to fulfill the requirements of section 303(c)(2)(B) for the Clean Water Act in the State of California. The State Policy for Implementation of Toxics Standards for Inland Surface Waters, Enclosed Bays, and Estuaries (effective May 22, 2000) established a standardized approach for permitting discharges of toxic pollutants to non-ocean surface waters in a manner that promotes statewide consistency.
The EPA and State Water Resources Control Board have established antidegradation policies. The federal policy, which is set forth in 40 CFR 131.12, states that:
- Existing instream water uses and the water quality necessary to protect existing uses (e.g., fish spawning, municipal water supply, and warm water aquatic habitat) shall be maintained and protected; and
- Where the quality of waters exceeds levels necessary to support beneficial uses, that quality shall be maintained and protected unless the State finds that allowing water quality degradation is necessary to accommodate important economic or social development in the area in which the waters are located. In allowing water quality degradation, the State shall assure water quality is adequate to fully protect beneficial uses.
As required by 40 CFR 131.12, the State has developed an Antidegradation Policy that is consistent with the federal policy described above; the state policy is described in the Administrative Procedures Update of 2, July 1990 entitled Antidegradation Policy Implementation for NPDES Permitting. The Antidegradation Policy applies to inland surface waters, ocean waters, and groundwaters.
The State Antidegradation Policy includes a technical (water quality and beneficial use impacts) and a non-technical component (necessity for socioeconomic development, maximum public benefit).
Technical. According to the Antidegradation Policy, the evaluation of project impacts on many water quality constituents is necessary to evaluate impacts on water quality relative to appropriate water quality objectives and impacts on beneficial uses. The State Antidegradation Policy guidelines state that, for NPDES permitting, the antidegradation analysis is the responsibility of the Regional Board and that the Regional Board shall comment on notices of preparation (NOPs) to ensure that it has sufficient information to conduct the appropriate antidegradation analysis.
Non-technical. Determinations as to whether the proposed project "is necessary to accommodate important economic or social development" and whether "maximum public benefit" is not within the scope of this EIR.
Thus, a complete analysis of the consistency of the project with the Antidegradation Policy is not possible in this EIR, nor is it necessary according to the State Antidegradation Policy. Therefore, a specific antidegradation policy evaluation criterion was not developed. However, the technical information in this document is intended to provide the basis for any findings that the Regional Board may be required to make.
Goals, Objectives, and Policies
Table 4.3-3 identifies General Plan water quality and hydrology goals, objectives, and policies that provide guidance for water use patterns. The table also indicates which Water Quality and Hydrology evaluation criteria are responsive to each set of policies.
|
Table 4.3-3 |
||||
|
General Plan Goals, Objectives, and Policies – Water Quality and Hydrology |
||||
|
|
|
Document Numeric Reference |
|
Relevant Evaluation Criteria1 |
|
City of Lodi General Plan Policy Document |
Section 7. Conservation Element – |
Goal A |
To protect water quality in the Mokelumne River, Lodi Lake, and in the area’s groundwater basin. |
1 and 2 |
|
City of Lodi General Plan Policy Document |
Section 9. Health and Safety |
Goal A |
To prevent loss of lives, injury, and property damage due to flooding. |
3 |
|
City of Stockton General Plan Policy Document |
Water Facilities |
Goal 1 |
Conserve groundwater and surface water in order to ensure sufficient supplies of good quality water. |
1 and 2 |
|
City of Stockton General Plan Policy Document |
Flood Hazards |
Goal 1 |
To protect the community from the risk of flood damage. |
3 |
|
San Joaquin County General Plan 2010 Volume I: Policies/ Implementation |
Water Quality |
Policies 1 – 3 |
|
1 and 2 |
|
San Joaquin County General Plan 2010 Volume I: Policies/ Implementation |
Public Health and Safety |
Policies 1 and 3 |
|
3 |
Source: Parsons, 2001
1
See Table 4.3-4
Evaluation Criteria with Points of Significance
Evaluation criteria for water quality and hydrology are presented in Table 4.3-4.
|
Table 4.3-4 |
|||
|
Evaluation Criteria with Point of Significance – Water Quality and Hydrology |
|||
|
|
|
Point of Significance |
|
|
1. Will the project cause a degradation of surface water quality? |
Estimated project impact on receiving water quality relative to existing conditions |
Numeric and narrative objectives in the Basin Plan, Bay-Delta Plan, and CTR |
City of Lodi General Plan |
|
2. Will the project cause degradation of groundwater quality? |
Estimated project impact on groundwater quality relative to existing conditions |
Requirements for wastewater reuse in Title 22 and reclamation specifications in the Discharge Permit |
City of Lodi General Plan |
|
3. Will the project cause an increase in flooding resulting in loss of lives, injury, and property damage due to flooding? |
Estimated project impact on flooding relative to existing conditions |
Prevent an increase in flooding which could result in loss of lives, injury, and property damage due to flooding. |
City of Lodi General Plan |
Source: Parsons, 2001
This impacts analysis is based on a review of relevant technical reports and water quality data.
Environmental Consequences (Impacts) & Recommended Mitigation
This section describes potential water quality and hydrology environmental impacts and mitigation measures. Table 4.3-5 summarizes project impacts on water quality and hydrology.
| Table 4.3-5 | ||||
|
Evaluation Criteria |
Point of Significance |
Impact |
Type of Impact1 |
Level of Significance2 |
|
Will the project cause a degradation of surface water quality? |
Numeric and narrative objectives in the Basin Plan, Bay-Delta Plan, and CTR |
No exceedence of water quality objectives |
C, O&M |
¤ |
|
Will the project cause degradation of groundwater quality? |
Protection of the area’s groundwater basin |
No significant degradation of groundwater quality |
O&M |
¤ |
|
Will the project cause an increase in flooding resulting in loss of lives, injury, and property damage due to flooding? |
Prevent an increase in flooding which could result in loss of lives, injury, and property damage due to flooding. |
No increase in flooding over existing conditions |
O&M |
== |
|
|
|
||
|
|
|
|
|
|
|
|
|
|
|
|
|||
|
|
|||
a Pesticide and Fertilizer Management Program that will be developed to incorporate State Water Resources Control Board Technical Advisory Committee management recommendations for Irrigated Agriculture and Pesticides. Water Quality/Hydrology Project Measure 2 is integrated into the project to minimize offsite movement of pesticides. The measure includes, but is not limited to, the following:Impact: 4.3.1 Will the project cause a degradation of surface water quality?
Analysis: No Impact; No Project Alternative
Surface water quality will not change relative to existing conditions.
Potentially Significant; Other Project Alternatives
Included in the project are design and best management practices (BMPs) to insure that irrigation water will be confined to the project area and no runoff to surface waters will occur. It is estimated that approximately 2.85 MGD of secondary treated effluent, industrial wastewater, and groundwater are now being applied in the Project area, and that under Project conditions approximately 2.5 MGD of reclaimed water will be applied for irrigation purposes, a reduction of 0.35 MGD. The rate of application of irrigation water will not increase over existing conditions. Wastewater used for fire control will be limited in volume and duration of discharge. No wastewater from fire control should reach surface waters. Wastewater used for restroom toilets will be discharged to the City sewer system and will not directly enter surface water bodies. Therefore the impact of the project on surface waters from the use of wastewater is less than significant.
Assuming a runoff coefficient (C) of 0.1 (Lindberg, 2000) for alfalfa, corn and pasture, and an infiltration value of 0.033 (based on the current application rates), the runoff from the site’s current conditions with an irrigated acreage of 310 acres is approximately 1.023 acre-ft/day (Q=0.1*0.033 ft/day*310 acres). Using a runoff coefficient (C) of 0.15 (Lindberg, 2000) for turf, and an infiltration value of 0.011 (based on CIMIS data for Lodi), the runoff from the proposed condition with in irrigated acreage of 250 acres will be approximately 0.415 acre-ft/day (Q=0.15*.011 ft/day*250 acres). Therefore, runoff from application of irrigation water will not increase over existing conditions. Irrigation runoff will not increase over the existing conditions and will be retained onsite.
In addition, Water Quality/Hydrology Project Measure 2 (Agrochemical and Fertilizer BMP) is designed to prevent offsite movement of pesticides and nutrients. Water Quality/Hydrology Project Measure 2 is
Control pollutants at their source through the verification of the need and amount of pesticides and fertilizer through soil and plant tissue testing, utilization of Integrated Pest Management procedures, utilization of the least toxic, least soluble, least persistent agrochemical, and careful evaluation and application of the lowest amount of agrochemical that will achieve the management goal.
Reduce the mobilization of pollutants through control of soil erosion, irrigation runoff, and subflow.
Utilize, dilute, detoxify, or dispose of excess pollutants correctly through proper handling (mixing and storage) and disposal practices.
These water quality/hydrology project measures will insure that no degradation of water quality in surface waters will occur from project irrigation.
It is estimated that an average of approximately 510 million gallons of reclaimed water are now being applied annually in the project area and that under project conditions 430 million gallons of reclaimed water will be applied annually, a reduction of approximately 16 percent. In addition, the quality of water used for irrigation will improve with tertiary treatment plant improvements designed to insure that irrigation water will meet Title 22 requirements, and biosolids will no longer be applied in the project area. The project could cause indirect impacts to surface water quality if the reclaimed water and biosolids that are no longer applied in the Project area are improperly disposed of elsewhere. Mitigation Measure 4.3-1 (Reclaimed Water and Biosolid Disposal) will insure that reclaimed water and biosolids, which must be disposed elsewhere as a result of the project will be handled in a manner to insure protection of surface and groundwater quality.
Also included in the project description are measures (Water Quality/Hydrology Project Measure 3- Storm Water Detention) to ensure that drainage from stormwater will not increase above current conditions.
The City recommends that storm drainage facilities be designed for a storm return frequency of once in one hundred (100) years. Runoff volumes are computed, using the Rational Formula, as the product of runoff coefficient, rainfall depth and contributing area (Q=CiA). Calculations assume that the site is not saturated from previous rainfall. The site is currently farmed with alfalfa, corn, and pasture; a runoff coefficient (C) of 0.1 is assumed (Lindberg, 2000). The proposed project will be turf; a run off coefficient of 0.15 is assumed for non-hardscape surfaces. A hundred year storm of 3.6 inches (0.3 feet) has been used. The total project site area is 400 acre. The total coverage of hard surface areas (run off coefficient of 0.95) is approximately 150 acres.
Based upon the above factors and assumptions, the existing runoff from the site during the 100-year storm is approximately 20 acre-ft. Currently all runoff is routed through the treatment plant. The runoff from the same storm for the developed project site will be 74 acre-ft. Retention of runoff from the newly created impervious surfaces and irrigation on City-owned property will be in the vicinity of the project site. It is estimated that retention on City-owned property will require use of approximately 54 acres.
Rainfall intensity for the project is estimated from a typical intensity vs. duration curve as shown in Lindberg’s CE Reference Manual (2000). Volume of runoff = C*rainfall*area/12 (acre-ft): C=weighted runoff coefficient, 0.7. The allowable discharge of 242 cfs is based on an estimated time of concentration of 30 minutes. The volume of runoff vs. duration and allowable discharge vs. duration is plotted. The estimated volume of the retention basin is the maximum difference between the volume of runoff and the allowable discharge, 73 acre-ft.
The City will allow a storm water collection system design at a 10-year intensity (an allowable discharge of 145 cfs based on an estimated time of concentration of 30 minutes). Temporary ponding on-site will be necessary to accommodate the additional runoff of 107 cfs from the 100-year event. Assuming the design of a collection system for 10-year intensity, the estimated volume of an on-site retention basin for the 100-year event will be 61 acre-ft.
Table 4.3-6
10-year Storm Project Site Conditions
|
Duration |
Duration |
Intensity |
Depth |
Volume |
|
(min) |
(min/1000) |
(in/hr) |
(in) |
(acre-ft) |
|
5 |
0.005 |
9.8 |
0.82 |
19.06 |
|
10 |
0.01 |
8.95 |
1.49 |
34.81 |
|
15 |
0.015 |
7.5 |
1.88 |
43.75 |
|
30 |
0.03 |
6 |
3.00 |
70.00 |
|
60 |
0.06 |
4 |
4.00 |
93.33 |
|
120 |
0.12 |
2.2 |
4.40 |
102.67 |
|
180 |
0.18 |
1.6 |
4.80 |
112.00 |
|
360 |
0.36 |
1 |
6.00 |
140.00 |
|
720 |
0.72 |
0.7 |
8.40 |
196.00 |
Source: Parsons, 2001
C, weighted value (turf+hard surface) = 0.7 Area = 400acres
Table 4.3-7
Allowable Discharge Based on Existing Site Conditions
|
Duration |
Duration |
Duration |
Volume |
Volume |
|
(min) |
(min/1000) |
(sec) |
(cu-ft) |
(acre-ft) |
|
5 |
0.005 |
300 |
116,100 |
3 |
|
10 |
0.01 |
600 |
232,200 |
5 |
|
15 |
0.015 |
900 |
348,300 |
8 |
|
30 |
0.03 |
1,800 |
696,600 |
16 |
|
60 |
0.06 |
3,600 |
1,393,200 |
32 |
|
120 |
0.12 |
7,200 |
2,786,400 |
64 |
|
180 |
0.18 |
10,800 |
4,179,600 |
96 |
|
360 |
0.36 |
21,600 |
8,359,200 |
192 |
|
720 |
0.72 |
43,200 |
16,718,400 |
384 |
Source: Parsons, 2001
Time of Concentration = 30 min
C = 0.1 (agricultural land)
I = 3.6 in/hr
Area = 400 acres
Flow = 240 (acre-in)/hour 387 cfs

Although the amount of newly generated runoff is small in comparison to the size of the parcel, provisions will be made as part of the project to assure that it will have an insignificant effect on surface waters. A grading and drainage plan prepared by properly licensed personnel and implemented in conjunction with the project will assure that surface waters and properties in the vicinity are not adversely affected.
Best management practices during the construction phase of the project as specified in the Project Storm Water Pollution Prevention Plan (Water Quality/Hydrology Project Measure 4) will prevent erosion. A grading and drainage plan, in conjunction with other project plans and specifications, shall be prepared and submitted for approval by the City Engineer. Compliance with erosion control measures in Chapter 70 of the UBC during construction is required and the City Water/Wastewater Superintendent will provide monitoring. When developed, all areas of the project site will be landscaped or covered with structures or pavement, therefore erosion impacts will be less than significant
The impact of the project on surface water quality based on evaluation criterion 1 is potentially significant due to the potential for improper biosolid disposal.
Mitigation: 4.3-1: Reclaimed Water and Biosolid Disposal
The City of Lodi has developed a Wastewater Master Plan, which develops feasible alternatives for wastewater and biosolid disposal to accommodate projected future growth in the City of Lodi. These alternatives take into consideration the possible changes in disposal options with the development of the Project. The Discharge Permit will be amended as part of the tertiary treatment plant additions and the additional project uses.
The City of Lodi will insure that reclaimed water and biosolids, which must be disposed elsewhere as a result of the Project, will be handled in a manner to insure protection of surface and groundwater quality and to insure compliance with existing regulations for the protection of surface and groundwater quality. The City shall obtain 210 acres of agricultural land that is or will be within City limits for biosolid disposal to compensate for the biosolid disposal land to be used for the ProStyle Sports Complex. Plans to properly dispose of the wastewater must be approved by the City prior to Project construction.
After
Mitigation: Less than Significant; All Alternatives
Impact: 4.3.2 Will the project cause a degradation of ground water quality?
Analysis: No Impact; No Project Alternative
Wastewater reuse will not change relative to existing conditions.
Potentially Significant; Other Project Alternatives.
The rate of application of irrigation water will decrease (from an existing 2.85 mgd to a maximum 2.5 mgd with the project) over existing conditions and application of biosolids on the project site will be eliminated. The project could cause indirect impacts to ground water quality if the reclaimed water and biosolids that are no longer applied in the project area are improperly disposed of elsewhere. However, mitigation measure 4.3-1 (Reclaimed Water and Biosolid Disposal) will ensure that reclaimed water and biosolids that must be disposed elsewhere as a result of the project, will be handled in a manner that protects surface and groundwater quality. The water used for project irrigation will meet Title 22 regulations due to improvements to the treatment plant. In addition, Water Quality/Hydrology Project Measure 5 will insure that the use of wastewater will meet the reclamation specifications provided for in the Discharge Permit that will be amended to include the additional project uses and facilities.
Water Quality/Hydrology Project Measure 2 (described above under 4.3-1) is designed to prevent offsite movement of pesticides, and will also protect groundwater quality. Therefore, the impact of the project on groundwater based on evaluation criterion 2 is potentially significant.
Mitigation: See Mitigation Measure 4.3-1 listed above.
After
Mitigation: Less than Significant; All Alternatives
Impact: 4.3.3 Will the project cause loss of lives, injury, and property damage due to flooding?
Analysis: No Impact; All Alternatives
Potential flooding will not change relative to existing conditions. Because of the project measures designed to prevent runoff of irrigation water, no flooding from irrigation is anticipated. The project measures designed to insure that the peak flow rate of drainage from stormwater runoff will not increase over existing conditions will insure that no increase over existing conditions in flooding at any hydraulic restrictions located downstream of the project will occur. The storm water drainage system will be able to accommodate a 100-year storm (Water Quality/Hydrology Project Measure 3 Storm Water Detention). According to QUAD (1995 Draft Environmental Impact Report - California Youth Soccer Associates), the alfalfa and winter barley that is currently grown in the project area has a runoff coefficient of 0.1 while the project turf has a runoff coefficient of 0.15. This means that 90 percent of rainfall would typically infiltrate in an alfalfa and winter barley field, and 85 percent of rainfall would be expected to infiltrate turf. In addition, currently 790 acres (of 880 total acres of land able to be irrigated with treated water) are irrigated croplands, but with the project, approximately 250 acres will be turf and the remaining project area (150 acres) will be hard surface. Therefore, the project has the potential to increase runoff. Project measures will insure that the retention (and therefore infiltration) time of the stormwater is increased over existing retention time, thus reducing runoff to pre-project levels. Water Quality/Hydrology Project Measure 3 (described above) specifies that the peak stormwater runoff rate and runoff volume won’t increase over current conditions, thereby preventing an increase in flooding. Therefore, no loss of lives, injury, or property damage will occur with a 100-year storm. The project area is located outside the 100-year flood plain, therefore the project will not cause the 100-year flood elevation to increase as a result of fill placement. Therefore no impact of the project on hydrology will occur based on evaluation criterion 3.
Mitigation: No mitigation is needed.
Cumulative impacts are defined as two or more individual effects which, when considered together, are considerable or which compound or increase other environmental impacts. There are no nearby projects within the Lodi city limits. Four projects will be located in adjacent San Joaquin County lands. These projects will result in increased land coverage and therefore, possible increases in urban runoff during storm events.
Under project conditions, the quality of water used for irrigation is improved (through treatment plant upgrades) and reduced in volume. Therefore, the project provides a net improvement to surface and ground water quality and no cumulative impacts on surface and ground water quality will occur. The project will not change stormwater volume or peak flow relative to existing conditions and the project will not cause the 100-year flood elevation to increase as a result of fill placement. Since potential flooding will not change relative to existing conditions, no cumulative impacts on flooding will occur.